Rajesh, in his printing press, got an order to print some books, out of which he completed 17/27 of the order in 34 days. In how many days, did he complete the entire order of printing?

SSC · 2024 · Quantitative Aptitude
Question:
Rajesh, in his printing press, got an order to print some books, out of which he completed 17/27 of the order in 34 days. In how many days, did he complete the entire order of printing?

Options

(1) 60
(2) 20
(3) 54
(4) 56
Answer: (3) 54

Explanation:
If 17/27 work takes 34 days, total work takes 34 × (27/17) = 54 days